TBM
Shield TBM
Hard Rock
Slurry Balance
Earth Balance
Rectangular
Auger Boring
Microtunnelling Machine
Others
2016-06-25
operation department
Date: June 24th, 2016
Project Name: He Liu traction station 220KV power supply project of Wuhuang intercity railway
Pipe Diameter: 2400mm
Pipe: reinforced concrete pipe
Length: 350 meters
soil Condition: rock, gravel
![]() |
![]() |
A Perfect Breakthrough for “Jiaolong No.2” Hard Rock Pipe Jacking Machine
A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia
A Perfect Breakthrough for the First Section of Sewage Pipe Network in Moscow, Russia
sales@tangxing.cn
086-5542796608