2016-06-25
operation department
Date: June 24th, 2016
Project Name: He Liu traction station 220KV power supply project of Wuhuang intercity railway
Pipe Diameter: 2400mm
Pipe: reinforced concrete pipe
Length: 350 meters
soil Condition: rock, gravel
sales@tangxing.cn
086-5542796608