2025-11-07
Operation Department
Date: November 2025
Location: Guangdong Province, China
Project Name: Huanbei Guangdong Project
Project Type: Water Supply Project
Equipment: Tangxing Technology HRC 2200mm Rock Pipe Jacking Machine
Jacking Distance: 650 meters
Geology: Fully weathered basalt soil and strongly weathered basalt strata
Project Challenges: The pipe jacking section passes beneath multiple major access roads in Yingli Town, closely adjacent to residential buildings and the G207 National Highway. The primary geological strata consist of fully weathered basalt soil and strongly weathered basalt, with fully weathered rock. The overall construction environment is highly complex.
Project Significance: This successful launch provides valuable technical experience for upcoming long-distance pipe jacking sections exceeding 500 meters. It serves as an important demonstration for improving efficiency and accelerating the overall construction progress of the project.

The 1,148-meter Pipe Jacking Section of the Foshan Xuda Power Tunnel Project Has Been Successfully Completed
"Huanbei Guangxi No. 8 (Shield Tunneling)" Hard Rock Shield TBM Successfully Launched
Jinan Metropolitan Circle Expressway West Ring Pipe Jacking Project Successfully Launched