2025-09-30
Operation Department
Date: September 2025
Construction Location: Foshan City, Guangdong Province
Project Name: Foshan Xuda Power Tunnel Project
Project Type: Power Engineering
Equipment Details: Tangxing Technology HRC 2800mm Rock Pipe Jacking Machine
Jacking Distance: 1,148 meters
Geological Conditions: Composite geology of silty clay, rocky strata, and oyster shell attachment layers
Project Challenges: Underpassing municipal roads, waterway channels, park structures, and side-crossing a water overpass bridge, with significant challenges including ultra-long distance, dual-section curves, deep burial, and high-risk factors.
Project Significance: The successful completion of the section between working shafts #7 and #8 is a key milestone in the construction of the Foshan Xuda Power Tunnel project. It not only marks significant progress but also serves as a valuable practical experience in long-distance pipe jacking technology under complex geological conditions. This experience provides crucial technical support for the construction of working shafts #2 to #3, accelerating the overall progress of the project.
![]() |
![]() |
"Huanbei Guangxi No. 8 (Shield Tunneling)" Hard Rock Shield TBM Successfully Launched
Jinan Metropolitan Circle Expressway West Ring Pipe Jacking Project Successfully Launched
Launch of the Pipe Jacking Machine for the Second Phase of the Yangtze River to Huaihe River Water Diversion Project (Water Conservancy Section) Hefei 5th Water Plant Pipeline Project
sales@tangxing.cn
086-5542796608