2023-09-25
Operation Department
Date: September 2023
Location: Malaysia
Project Name: The Second Phase of the Kuching Sewage Treatment System in East Malaysia
Project Type: Sewage pipe network project
Equipment Details: Tangxing Technology HRC 1500mm hard rock pipe jacking machine
Geology: Hard rock, rock hardness up to 100 to 130 MPa
Jacking Distance: 240 meters
Difficulties: The working shaft is 35 meters deep with abundant groundwater. It has difficulties such as large soil depth, high rock hardness, and a large wear coefficient, which requires high wear resistance of the cutter head.
Significance: The completion of The Second Phase of the Kuching Sewage Treatment System in East Malaysia will effectively ease the lives of residents in the jurisdiction and solve problems such as pollution caused by sewage flowing into rivers.
![]() |
![]() |
![]() |
![]() |
A Perfect Breakthrough for “Jiaolong No.2” Hard Rock Pipe Jacking Machine
A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia
A Perfect Breakthrough for the First Section of Sewage Pipe Network in Moscow, Russia
sales@tangxing.cn
086-5542796608