2023-07-10
Operation Department
Date: July 2023
Location: Shijiazhuang City, Hebei Province
Project Name: Oil Pipeline Project (Crossing the South-to-North Water Diversion Project)
Project Type: Oil Pipeline Network Project
Equipment: Tangxing Equipment HRC 1800mm hard rock pipe jacking machine
Geology: Pebble
Jacking Distance: 220 meters
Difficulties: Rich groundwater, 32 meters of soil cover, and pipe jacking across the river. In the early stage of the project, the pipe jacking machine failed due to the use of equipment from other companies. Later, the Tangxing pipe jacking machine was used for rescue.
Significance: The completion of the project marks Tangxing Equipment's high-quality products and advanced hard rock excavation technology. After the project is completed, it will be of great significance to effectively promote regional economic development and ensure energy supply.
![]() |
![]() |
![]() |
![]() |
Successful Launch of Pipe Jacking Between Shaft No. 8 and Shaft No. 7 of the Huanbei Guangdong Project (Section D4)
The 1,148-meter Pipe Jacking Section of the Foshan Xuda Power Tunnel Project Has Been Successfully Completed
"Huanbei Guangxi No. 8 (Shield Tunneling)" Hard Rock Shield TBM Successfully Launched







sales@tangxing.cn
086-5542796608