2022-04-22
operation department
Date: June 2020
Location: Ji'an City, Jiangxi Province
Project Name: Ji'an Central City Emergency Water Source Construction Project
Equipment: 1200 rock MTBM
Geology: rock
Jacking Distance: 853 meters
Difficulties: Crossing the Ganjiang River, with abundant groundwater and high water pressure, it is impossible to open warehouses and change tools, long-distance construction, strict requirements for axis control, no deviation, and steel pipe welding technology requirements to be foolproof.
![]() |
![]() |
Successful Launch of Pipe Jacking Between Shaft No. 8 and Shaft No. 7 of the Huanbei Guangdong Project (Section D4)
The 1,148-meter Pipe Jacking Section of the Foshan Xuda Power Tunnel Project Has Been Successfully Completed
"Huanbei Guangxi No. 8 (Shield Tunneling)" Hard Rock Shield TBM Successfully Launched