2014-05-14
operation department
Date: May, 2014
Project Name: Beijing Drain Gas Blanking Project
Pipe Diameter: 1800mm
Pipe: reinforced concrete pipe
Length: 250 meters
soil Condition: clay
Challenges: The current situation is constructing on the road, the environment is complicated, and the site is narrow
![]() |
![]() |
![]() |
![]() |
A Perfect Breakthrough for “Jiaolong No.2” Hard Rock Pipe Jacking Machine
A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia
A Perfect Breakthrough for the First Section of Sewage Pipe Network in Moscow, Russia