Date: April, 2009
Project Name: Beijing-Guangzhou Railway Sewage Pipeline Project
Pipe Diameter: 2000mm
Pipe: reinforced concrete pipe
Length: 108 meters
Soil Condition: silt
Challenges: Crossing railroads and canals
![]() |
![]() |
![]() |
![]() |
The Rectangular Pipe Jacking Machine of Nanchang Rail Transit Project Launched Smoothly
The Zhaoshi River Pipe Jacking Tunnel Crossing Project in the Sixth Bid Section of the Middle Section of the West-East Gas Transmission Line 3 Launched Smoothly
Bengbu Long-distance Pipe Jacking Project Started Smoothly