A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia

  • 2025-04-02

  • Operation Department

Date: February 2025

Location: Ulaanbaatar, Mongolia

Project name: Ulaanbaatar Water Diversion Project

Project type: Water Diversion Project

Equipment details:Tangxing Technology HRC1200 rock pipe jacking machine

Jacking distance: 240 meters of the first jacking section was successfully completed

Difficulties: sand and pebble geology, rich groundwater, crossing the river

Project significance: It can help Ulaanbaatar to crack the bottleneck of water shortage and ensure the sustainable development and ecological safety of the city.





Submit your requirements quickly in 30 seconds, and
customize your industry-specific solutions online
Name
Contact Information
Leave a Message
Submit Now
Service Hotline
086-5542796608
CONTACT US
  • EUROPE
    Tangxing_Edward
    +6010-397 6995
    T1SERVICE@TANGXING.CN
  • MIDDLE EAST OR ASIA
    Tangxing_Michael
    +6010-293 6995
    T2SERVICE@TANGXING.CN
  • AFRICA
    Tangxing_Bonnie
    +6010-825 6995
    T3SERVICE@TANGXING.CN
  • AMERICAS
    Tangxing_lvy
    +8615305547358
    IVY@TANGXING.CN
  • Anhui Tangxing Equipment Technology Co., Ltd (Hungary branch office)
    Sales representative_Leo Lee
    +0036304170973
    WWW.TANGXINGGLOBAL.COM
    TANGXINGEUROPA@GMAIL.COM

sales@tangxing.cn

086-5542796608