TBM
Shield TBM
Hard Rock
Slurry Balance
Earth Balance
Rectangular
Auger Boring
Microtunnelling Machine
Others
2024-12-04
Operation Department
Date: November 2024
Location: Wenzhou
Project Name: Wenzhou Oujiang River Water Diversion Project
Project Type: Water diversion project
Equipment Details: Tangxing Technology HRC4000 rock pipe jacking machine
Geology: Mainly composed of sand pebbles and mud pebbles
Jacking Distance: There are three jacking sections, with a cumulative jacking distance of about 150 meters
Project Difficulties: The construction conditions along the line are complex, and the pipe jacking machine needs to cross the busy national highway during the excavation process, which requires high control of ground subsidence.
Project Significance: The Oujiang River Water Diversion Project is a key water conservancy and livelihood project in Zhejiang Province. It is also the largest investment, the longest water diversion tunnel, and the largest water diversion flow in Wenzhou City. After its completion, it will greatly alleviate the water use problem in Wenzhou City.
The Pipe Jacking Section of Railway Project of "Wangjia Dajing" Water Source Emergency Replacement Project Was Completed
Anhui Province Gangkouwan Reservoir Irrigated Area Project Launched
The New Xiangyun River West Line Project in Pingdingshan City Launched Smoothly
sales@tangxing.cn
086-5542796608