2024-12-04
Operation Department
Date: November 2024
Location: Wenzhou
Project Name: Wenzhou Oujiang River Water Diversion Project
Project Type: Water diversion project
Equipment Details: Tangxing Technology HRC4000 rock pipe jacking machine
Geology: Mainly composed of sand pebbles and mud pebbles
Jacking Distance: There are three jacking sections, with a cumulative jacking distance of about 150 meters
Project Difficulties: The construction conditions along the line are complex, and the pipe jacking machine needs to cross the busy national highway during the excavation process, which requires high control of ground subsidence.
Project Significance: The Oujiang River Water Diversion Project is a key water conservancy and livelihood project in Zhejiang Province. It is also the largest investment, the longest water diversion tunnel, and the largest water diversion flow in Wenzhou City. After its completion, it will greatly alleviate the water use problem in Wenzhou City.
![]() |
![]() |
A Perfect Breakthrough for “Jiaolong No.2” Hard Rock Pipe Jacking Machine
A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia
A Perfect Breakthrough for the First Section of Sewage Pipe Network in Moscow, Russia
sales@tangxing.cn
086-5542796608