2022-08-12
operation department
Date: July 2022
Location: Jinan City, Shandong Province
Equipment: Tangxing SPB2600mm slurry balance pipe jacking machine
Type: Power engineering
Geology: Soft soil
Jacking Distance: 280 meters
Difficulties: the total jacking distance is more than 1,000 meters, and the project is divided into multiple jacking sections, complex geology
Significance: After the project is completed, it will produce great social benefits and further improve the local infrastructure construction.
![]() |
![]() |
![]() |
![]() |
Jinan Metropolitan Circle Expressway West Ring Pipe Jacking Project Successfully Launched
Launch of the Pipe Jacking Machine for the Second Phase of the Yangtze River to Huaihe River Water Diversion Project (Water Conservancy Section) Hefei 5th Water Plant Pipeline Project
Successful Breakthrough of the Second Water Treatment Plant Relocation Project (First Section) in Wanan County, Jiangxi