2022-05-09
operation department
Date: May 2022
Location: Chengdu
Equipment: HRC2400 rock microtunneling machine
Type: water diversion project
Geology: pebble, rock
Jacking Distance: about 150 meters
Difficulties: long jacking distance, complex geology in the crossing section
Significance: The total investment of the water diversion project is about 1.8 billion CNY, which is jointly funded by Sichuan Province, Chengdu City and Ziyang City. It is a key water conservancy project. After the project is completed, it can solve the livelihood project of drinking water safety for 400,000 people in Ziyang City.
![]() |
![]() |
![]() |
![]() |
Launch of the Pipe Jacking Machine for the Second Phase of the Yangtze River to Huaihe River Water Diversion Project (Water Conservancy Section) Hefei 5th Water Plant Pipeline Project
Successful Breakthrough of the Second Water Treatment Plant Relocation Project (First Section) in Wanan County, Jiangxi
Jinan 2×660,000 kW Advanced Coal-Fired Unit Heating Project Pipeline Engineering