2022-05-09
operation department
Date: May 2022
Location: Chengdu
Equipment: HRC2400 rock microtunneling machine
Type: water diversion project
Geology: pebble, rock
Jacking Distance: about 150 meters
Difficulties: long jacking distance, complex geology in the crossing section
Significance: The total investment of the water diversion project is about 1.8 billion CNY, which is jointly funded by Sichuan Province, Chengdu City and Ziyang City. It is a key water conservancy project. After the project is completed, it can solve the livelihood project of drinking water safety for 400,000 people in Ziyang City.
![]() |
![]() |
![]() |
![]() |
The Rock Pipe Jacking Machine for the Expansion and Reconstruction Project of the Main Sewage Pipe in the South of Changsha Economic and Technological Development Zone Launched Smoothly
A Perfect Breakthrough for the Pipe Jacking Section of Oil Pipeline Project (Crossing the South-to-North Water Diversion Project)
The Pipe Jacking Machine of the Sewage Pipe Network Renovation and Repair Project in Shushan District, Hefei City Started Smoothly
sales@tangxing.cn
086-5542796608