2022-05-09
operation department
Date: May 2022
Location: Chengdu
Equipment: HRC2400 rock microtunneling machine
Type: water diversion project
Geology: pebble, rock
Jacking Distance: about 150 meters
Difficulties: long jacking distance, complex geology in the crossing section
Significance: The total investment of the water diversion project is about 1.8 billion CNY, which is jointly funded by Sichuan Province, Chengdu City and Ziyang City. It is a key water conservancy project. After the project is completed, it can solve the livelihood project of drinking water safety for 400,000 people in Ziyang City.
![]() |
![]() |
![]() |
![]() |
Jinan 2×660,000 kW Advanced Coal-Fired Unit Heating Project Pipeline Engineering
A Perfect Breakthrough for Xidian Binhaixi River Box Culvert Jacking Project Across Shenhai Expressway
A Perfect Breakthrough for “Jiaolong No.2” Hard Rock Pipe Jacking Machine
sales@tangxing.cn
086-5542796608